Fire curtains let a building keep its open floors, atria and wide openings while still meeting its fire strategy. Vivid Finishes delivers fire curtain installation as part of a coordinated fire protection package on commercial fit-outs and refurbishments across London, planned with the fire engineer, the main contractor and the trades around the opening.
Modern commercial interiors are designed around openness: connecting stairs between office floors, atria, wide reception spaces and open-plan floors that run from core to façade. Fixed fire-resisting walls and doors often work against that design. Fire curtains give the fire engineer another option.
A fire curtain is a fire-resisting fabric barrier. Depending on the type, it either stays hidden in a headbox until a fire is detected and then descends to close the opening, or it is fixed permanently in a concealed space to close it. Either way, it only works if the compartment around it is complete: the wall above the headbox, the void above the ceiling and every service penetration nearby.
That last point is where many curtain installations fall short, and it is why we treat a curtain as part of the compartment, not a standalone product.
The open, high-specification spaces fire curtains are designed to protect.
104 Park Street, Mayfair: painting and decorating by Vivid Finishes.Both get called fire curtains. They are specified, installed, tested and maintained in completely different ways, so confusing them is one of the costliest mistakes in a fire protection package.
| Automatic (active) fire curtain | Fixed flexible fire barrier curtain | |
|---|---|---|
| How it works | Stored in a steel headbox and released to descend when the fire alarm or a local detector signals | Installed permanently in position, with no moving parts |
| Typical locations | Openings in compartment walls, atria, lift lobbies, open-plan floors | Ceiling voids, roof voids and other concealed spaces |
| Product standard | BS 8524-1 specification and BS 8524-2 code of practice for application, installation, commissioning and maintenance | Tested and classified as a fire barrier; the rating comes from the system's test evidence |
| Interfaces | Fire alarm cause and effect, power supply and battery backup, control panel, floor obstruction zone | Structure, fixings, and fire stopping to services passing through |
| Commissioning | Required, including a check that the curtain closes under gravity if power is lost | Inspection and record of installation |
| Ongoing maintenance | Regular inspection and servicing under a maintenance regime | Inspection whenever the void is opened or altered |
If a fixed flexible barrier is what your void needs, our fire barrier installation page explains how we deliver it. If you need an opening protected with an automatic curtain, the specification questions below decide the product.
We deliver commercial fire curtains across London as part of our passive fire protection packages, alongside the fire stopping and fire barriers that make the curtain's compartment complete. Systems we work with include FireFly and Envirograf. At quotation, we confirm in writing which system is proposed, who installs each part, and who is responsible for alarm connection, commissioning and maintenance.
Cat A and Cat B floors where an open layout or a connecting stair needs an alternative to a fixed compartment wall.
Existing buildings being reconfigured, where new openings in compartment walls have to be protected without rebuilding the core.
Receptions, atria and hospitality spaces where the curtain must disappear into the ceiling design and the headbox must be finished to match.
Flexible barriers in ceiling and roof voids where the geometry or services make a rigid barrier impractical.
Curtains, barriers and fire stopping, planned as one compartment.
Senator House, Victoria: fire protection by Vivid Finishes, delivered out of hours in an occupied building.A fire curtain is the one part of passive fire protection that has to move on the day. Everything around it has to be ready for that moment.
Most delays on curtain packages come from questions nobody answered at design stage. These are the ones we work through with your fire engineer and design team.
Fire curtains are most often specified where open floors, atria and premium finishes leave no room for a fixed wall. These are the kinds of interiors our teams finish.



We review the fire strategy, drawings and opening schedule with your team and the fire engineer, and confirm the curtain type for each location.
Opening sizes, headbox space, fixing substrates and interfaces are surveyed. Responsibilities for each part are set out in writing.
Installation is sequenced with the ceiling, M&E and fire alarm trades, with fire stopping and barriers completed around each curtain.
Curtains are installed, inspected and, where in scope, commissioned. Records, product data and maintenance information go into the O&M.
A curtain that closes perfectly will still fail if smoke and fire can pass over the headbox through an unsealed ceiling void, or around it through unsealed services. That is why we deliver curtains alongside fire stopping and fire barriers: the curtain, the construction above it and the penetrations around it are planned, installed and recorded together.
Because we also spray and decorate, the finishes around headboxes and side guides are planned with the curtain, not left for a different trade to patch around later.
We plan access, containment and out-of-hours working with the main contractor before work starts. At Senator House, Victoria, our fire protection team worked out of hours in a building that still had tenants. That was an intumescent coatings package, but the same planning applies to curtain installations in occupied buildings.
Headboxes that disappear into the finished ceiling.
Taj Hotel, St James' Court: 15-month refurbishment by Vivid Finishes, phased around a live hotel.A fire curtain's rating comes from its test evidence and classification, not its product name, and the records have to follow it into the building's life.
Automatic fire curtains are covered by the BS 8524 series, republished in 2025. Part 1 is the product specification, including cycle testing and motor testing at elevated temperatures. Part 2 covers application, installation, commissioning and maintenance. Products should hold third-party certification from a UKAS-accredited body.
We check that the proposed system's evidence covers the size, orientation and fixing substrate of each opening. If it does not, we raise it with the fire engineer before ordering. At completion, Regulation 38 information, including installation and commissioning records, operating instructions and maintenance requirements, goes into the O&M.
If your specification asks for a particular installer certification scheme for fire curtains, tell us at enquiry and we will confirm what we can provide for that package before you commit.
A curtain only works when the compartment around it is complete.
Fire protection to a steel connection by Vivid Finishes.A fire curtain is a fire-resisting fabric barrier used to protect an opening or divide a space in a fire. Some products are tested as combined fire and smoke curtains, while dedicated smoke curtains are a separate product type. Automatic fire curtains are stored in a headbox and descend when the fire alarm or a detector signals. Fixed flexible barriers are installed permanently in concealed spaces such as ceiling and roof voids.
An automatic curtain moves: it is released on a fire signal, needs a power supply and control panel, must be commissioned and needs regular servicing. A fixed flexible barrier does not move: it permanently closes a void, much like a rigid fire barrier. They are tested, specified and maintained differently, so the fire strategy should state which is required at each location.
In some situations, yes, but only where the fire strategy allows it and building control accepts it. The fire engineer decides whether a curtain is an acceptable alternative at each location, and what performance it must achieve.
The BS 8524 series, republished in 2025. Part 1 is the product specification and Part 2 is the code of practice for application, installation, commissioning and maintenance. Dedicated smoke curtains are covered separately by BS EN 12101-1.
Automatic fire curtains need regular inspection and servicing to confirm they will deploy when required, including the gravity fail-safe. The maintenance regime should be set out in the O&M and agreed with the building's facilities team at handover.
Yes, subject to survey. Headbox space in the existing ceiling void, fixing substrates and the alarm interface need checking first. We plan access and out-of-hours working with the main contractor so installation can happen around occupants.
This varies by project and is often split between the curtain installer and the fire alarm contractor. We confirm responsibilities for alarm interface, power supply, commissioning and maintenance in writing at quotation, so nothing falls between trades.
The fire strategy or the required performance for each curtain, drawings showing each opening with clear sizes, ceiling void depths, the fixing substrates, details of the fire alarm system, site access and your programme.
Send your drawings and fire strategy and we will confirm the right curtain type for each opening, how we would sequence the installation and who is responsible for each part. Our lines are open 9am to 5pm, Monday to Friday.
Email info@vividfinishes.co.uk with: